Den Restoration Sub-Project Meeting Sunday April 29, 2007

















SUMMARY
1) Den restoration project

(a) Targetted to be done during the 2 week school holidays from around end of May to early June 2007, preferably in no more than 10 days.

(b) Current ESG to prepare, carry out and submit the following by 1st week of May 2007
(i) Plans and requirements
(ii) Simple scaffolding structures on the side
(iii) Remove the many pieces of wood beside the Den as clear out the other items in the Den compound,
(iv) Current ESG advised not to proceed with their intention to proceed with
chopping of the big trees

(c) Den restoration project is planned to cover the following areas:
(i) Roof leaks
(ii) Re-wiring and lighting
(iii) Toliot repairs
(iv) Required structural repairs
(v) Paint job
(vi) Soil erosion problem on the side

(d) As a matter of courtesy to SJI authorities, inform En Megat, SJI BOG Chairman, once things are quite finalised.